Attached is the proposed schedule for a school musical next year.
Practices would start before the first day of school and performances would be the third weekend in September.
Mr. Bridges will direct and Mr. Sundleaf will assist.
Not all of the night practices can be guaranteed, but the morning practices will be minimal until school athletics contests start at the end of August.
The musical that has been selected is one hour in length, so practices can be shorter than a typical musical would require.
-->
Schedule for School Musical
Monday, August 11 Practice
begins
August 11-15 Nights
are available for practices
August 18-21 Nights
are available for practice
August 22 a.m.
practice
August 25-28 Nights
are available for practice
August 29 a.m.
practice
Sept 2-5 a.m.
practices
Sept. 8-11 a.m.
practices
Sept. 15-17 a.m.
practices
Thursday, September 18 Performance
Date
Saturday, September 20 Performance
Date