The school board resumed the monthly board meeting Tuesday night at 7:00 pm. Representatives from low bidder Crafts Inc of Norfolk went through their proposal and answered questions from the board. The classroom addition will be a 3,120 square foot addition to the north side of the lower level of the existing building.
Concrete will include a sidewalk on the north and west ends of the new addition to connect to the existing sidewalk. The board will consider adding a concrete parking lot to the project west of the new addition. The building will rest on a concrete slab and will have a retaining wall on the east side.
Masonry will match the existing school lower level.
Insulation will be R-19 on exterior walls and R-38 on the roof.
Doors and windows will match the existing building.
The music room will be carpeted and the other rooms will have vinyl tile.
The current storm drain system will be moved.
The following costs were not included in the bid because the school chose to work with their existing system providers:
Fire sprinkler system, heating and air conditioning unit, and Data cables, fire alarm system and intercom system.
I am including a copy of the proposed Timeline in which work would start April 30 and be completed August 1.